Question: PLS ANS ASAP At a manufacturing cell in a pull production system using Kanban, the demand per week for the parts is 24000 units. The
PLS ANS ASAP
At a manufacturing cell in a pull production system using Kanban, the demand per week for the parts is 24000 units.
The average processing time is equal to 325 minutes. On average, the conveyance time between the cell to the downstream station is 3.5 hours. Container size is 275 units. The system operates 8 hours a day, 5 days a week.
A. Calculate the number of containers needed assuming 10 % safety stock is used. Put you answer here: Answer
containers
B. Calculate the actual safety stock being used in part A.
Put your answer here as a percentage but do not write the % in the answer