Question: pls help! (a) Compute ES, EF, LS, LF, slack for each activity. (7 points) (b) What is(are) the critical path(s) and the minimum time to
pls help!
(a) Compute ES, EF, LS, LF, slack for each activity. (7 points) (b) What is(are) the critical path(s) and the minimum time to complete the project? ( 3 points) Critical path(s): START ACG FINSH Minimum time to complete the project: 7+3+10=20 (c) Assume that variances for activity A,B, and C are 1 . The variances for activity D and E are 0.75. The variances for activity F,G and H are 2. What is the project standard deviation? Show your work. Round to three decimal points. (2 points) (d) Calculate the probability of completing the project in 19 weeks. ( 3 points)