Question: pls help Question 18 3 pts A research project is scheduled for implementation based on the network shown. The estimated activity times and number of

pls help
Question 18 3 pts A research project is scheduled for implementation based on the network shown. The estimated activity times and number of truck required for the research project is as indicated in Table 1. Activity Immediate Predecessors Activity Activity Expected Variance Time (te) Activity Standard Deviation No. of Truck Required (A) B D E F G H Estimate Activity Times (months) a m b 6 7 8 3 3 3 4 6 8 2 2 8 2 3 1 1.5 5 1.5 3 4.5 1 2 3 A B D.F B E,G (B) (C) D (E) (F) (d) (e) (f) eeseelalele ACT A =4 ACT B = 3 ACT C= 4 ACT D = 2 ACTE - 1 ACT F = 2 ACT G = 3 ACT H = 1 Table 1Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock