Question: pls show work Consider the following process (if you are using Safari, you may have trouble opening this image. Find it under Files). Assuming an

pls show work
pls show work Consider the following process (if
Consider the following process (if you are using Safari, you may have trouble opening this image. Find it under Files). Assuming an 8-hour workday, if the average number of Drilled parts waiting in W1 is 100 units, what would be the average waiting time of those parts in W1? Assembly Line 1 (140/hour) WI FG Final Assembly (160/hour) Drilling (200/hour) 64 min 37 min 45 min Correct! 43 min

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!