Question: plz answer according to the value given in the question 1. Activity Slack Activity Predecessor Activity Duration (In weeks) 3 a b 2 2 a

plz answer according to the value given in theplz answer according to the value given in the question

1. Activity Slack Activity Predecessor Activity Duration (In weeks) 3 a b 2 2 a N d b.c 1 e 3 f de 2 g d, f 4 h G 1 a) Draw an Activity on Node Diagram. Compute the early and Latest starting and finish time. Compute slack times. [1 + 2 = 3 marks] b) Find out the possible paths and the critical path. What are the critical activities? [1 mark] c) If we delay activity d' and 'e' by 3 days, how would it impact the project completion time? [1 mark]