Question: plzz answer a and b part clearly solve this. 1. Activity Cost per day to crash 500 300 A * B Preceding Normal Crash activity

plzz answer a and b part clearly solve this. 1.

plzz answer a and b part clearly solve this.

1. Activity Cost per day to crash 500 300 A * B Preceding Normal Crash activity Time Time 7 2 A 5 A 8 8 B, C 6 * B, C 3 1 D 7 4 E, F 3 1 Project's budget per day $500 D E F G 400 350 100 550 a. Draw an AON diagram based on the activities and their relationships given in the table. (2 Marks) b. Develop a crashing schedule [ Replace the * with any value in between 3-5]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!