Question: PM . 6 6 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his

PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:
Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 32 $1,100 $3,200-
B 21 $2,200 $2,560-
C 42 $1,200 $2,500-
D 73 $2,100 $2,500 A
E 63 $1,500 $2,100 B
F 42 $4,000 $5,380 C
G 42 $1,650 $2,100 D, E
What is the overall duration of the project?
14
Which of the following activities has the lowest crash cost per week?
C
A
E
D
Which of the following activities has the highest crash cost per week?
C
B
G
F
Incorrect
Your Answer:
G
If you wanted to shorten the overall duration of the project, which activity should you crash first?
A
E
C
B
D
What is the total cost of crashing the project from its current duration down to 11 weeks?
300
What is the total cost of crashing the project from its original duration to 9 weeks?
NumberPM. 66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After
gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:
What is the overall duration of the project?
Which of the following activities has the lowest crash cost per week?
C
A
E
D
Which of the following activities has the highest crash cost per week?
C
B
G
F
If you wanted to shorten the overall duration of the project, which activity should you crash first?
A
E
C
B
D
What is the total cost of crashing the project from its current duration down to 11 weeks?
What is the total cost of crashing the project from its original duration to 9 weeks?
 PM.66 Real estate developer Russell Call was working with a few

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!