Question: PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination:

PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination:
Activity Duration (days) Immediate Predecessor(s)
A 6 -
B 12 -
C 5 -
D 4 A
E 2 C
F 11 B,D,E
G 15 D,E
H 6 F
I 7 G,H
J 18 I
What is the overall duration of the project (in days)?
What is theearliestday you couldstartactivity J? (Write the day number in the field below.)
What is theearliestday you couldfinishactivity G?
What is thelatestday you couldstartactivity C?
What is thelatestday you couldfinishactivity B?
What is theslacktime for activity D?
What would be the overall duration of the project if activity H were increased by 2days, from 7to 9days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!