Question: PMAN 6 5 0 Session 5 Individual Assignment ( v 3 . 1 ) Earned Value Management Introduction All of you have had at least

PMAN 650 Session 5 Individual Assignment (v3.1) Earned Value Management Introduction All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results. In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS - DO NOT USE MICROSOFT PROJECT. Problem Background Your project consists of seven activities with planned start and finish datesshown in the chart below: Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Activity 6 Activity 71357911131517192123 Week
PMAN 650 Session 5 Individual Assignment (v3.1) Earned Value Management Activity budgets and earned value (EV) accrual rules from you project cost management plan are as follows: ActivityBudgetEV Accrual Rule 125,000 Percent Complete with Gates 220,000 Fixed Formula -0/100350,000 Weighted Milestones 460,000 Percent Complete with Gates 530,000 Fixed Formula -40/60620,000 Fixed Formula -30/70710,000 Fixed Formula -100/0 Assumptions 1.Assume a five-day work week with no holidays occurring during the work week. 2.For all activities (except activities 3 and 4), assume the expenditure rate is constant over the duration of the activity, i.e., the amount planned to be spent each week is the same. See the conceptual profile below. Expenditure Rate 123456... and so on WeekWeekly Expenditures - Constant Expenditure Rate Activities
PMAN 650 Session 5 Individual Assignment (v3.1) Earned Value Management 3.For activity 3, the planned expenditure profile is shown below: 010002000300040005000600070008000900012345678 Activity 3 Weekly Planned Expenditures 4.For activity 4, the planned expenditure profile is shown below: 02000400060008000100001200012345678Activity 4 Weekly Planned Expenditures
PMAN 650 Session 5 Individual Assignment (v3.1) Earned Value Management The project sponsor wants you (the PM) to present a project cost and schedule performance assessment using data through the end of week 8: ActivityActual StartActual FinishExpended 1Start of week 1End of week 522,0002Start of week 6End of week 825,0003Start of week 340,0004Start of week 88,000506070 For activity 1, three equally-valued gates have been established and all gates are complete as of the end of week 8. For activity 3, five milestones have been established with the following values: (1) milestone 1-10%; milestone -20%; milestone 3-15%; milestone 4-20%; milestone 5-35%. Four of the milestones are complete as of the end of week 8. For activity 4, four equally values gates (milestones) have been established. As of the end of week 8, none of the gates have been reached but the activity owner estimates 30% of the work required to reach the first gate has been accomplished. Answer the questions that follow. Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.
PMAN 650 Session 5 Individual Assignment (v3.1) Earned Value Management 1.Earned Value Measures a.Calculate earned value measures for each activity and for the cumulative project as of the end of week 8; fill in the table below: ActivityPlanned Value (PV)Earned Value (EV)Actual Cost (AC) Activity One22,000 Activity Two25,000 Activity Three40,000 Activity Four8,000 Activity Five0 Activity Six0 Activity Seven0 Entire Project
PMAN 650 Session 5 Individual Assignment (v3.1) Earned Value Management 2.Earned Value Performance Measures a.Calculate earned value performance parameters for each activity and for the cumulative project as of the end of week 8; fill in the table below: ActivitySchedule Variance (SV)Schedule Performance Index (SPI)Cost Variance (CV)Cost Performance Index (CPI) Activity One Activity Two Activity Three Activity Four Activity Five Activity Six Activity Seven Entire Project b.Is the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why? c.Is the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why? 3.Earned Value Forecasts a.What is the value of the "Cumulative CPI" Estimate-at-Completion (EAC)? b.Using the "Mathematical" or "Overrun to Date" Estimate-at Completion, what is the value of the Estimate-to-Complete (ETC)? c.Using the "Cumulative CPI times SPI" Estimate-At-Completion, how much more or less money (other than the current budgeted amount) will you need to finish the project? d.How much would the Cost Performance Index (CPI) have to change in order to complete the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!