Question: PMAN 6 5 0 Session 5 Individual Assignment ( v 3 . 1 ) Earned Value Management Introduction All of you have had at least
PMAN Session Individual Assignment v Earned Value Management Introduction All of you have had at least an introduction to earned value management in the project management fundamentals course. Many of you may have had the opportunity to use earned value management in your professional careers. In practice, most EVM analysis results are generated by scheduling software or other applications. As a project manager, you must have a good handle on the concepts and be able to verify the accuracy of EVM analysis results. In this assignment, you will have an opportunity to brush up and expand upon your EVM knowledge and skills by applying EVM concepts to a practical problem. THIS ASSIGNMENT REQUIRES A MANUAL ANALYSIS DO NOT USE MICROSOFT PROJECT. Problem Background Your project consists of seven activities with planned start and finish datesshown in the chart below: Activity Activity Activity Activity Activity Activity Activity Week
PMAN Session Individual Assignment v Earned Value Management Activity budgets and earned value EV accrual rules from you project cost management plan are as follows: ActivityBudgetEV Accrual Rule Percent Complete with Gates Fixed Formula Weighted Milestones Percent Complete with Gates Fixed Formula Fixed Formula Fixed Formula Assumptions Assume a fiveday work week with no holidays occurring during the work week. For all activities except activities and assume the expenditure rate is constant over the duration of the activity, ie the amount planned to be spent each week is the same. See the conceptual profile below. Expenditure Rate and so on WeekWeekly Expenditures Constant Expenditure Rate Activities
PMAN Session Individual Assignment v Earned Value Management For activity the planned expenditure profile is shown below: Activity Weekly Planned Expenditures For activity the planned expenditure profile is shown below: Activity Weekly Planned Expenditures
PMAN Session Individual Assignment v Earned Value Management The project sponsor wants you the PM to present a project cost and schedule performance assessment using data through the end of week : ActivityActual StartActual FinishExpended Start of week End of week Start of week End of week Start of week Start of week For activity three equallyvalued gates have been established and all gates are complete as of the end of week For activity five milestones have been established with the following values: milestone ; milestone ; milestone ; milestone ; milestone Four of the milestones are complete as of the end of week For activity four equally values gates milestones have been established. As of the end of week none of the gates have been reached but the activity owner estimates of the work required to reach the first gate has been accomplished. Answer the questions that follow. Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.
PMAN Session Individual Assignment v Earned Value Management Earned Value Measures aCalculate earned value measures for each activity and for the cumulative project as of the end of week ; fill in the table below: ActivityPlanned Value PVEarned Value EVActual Cost AC Activity One Activity Two Activity Three Activity Four Activity Five Activity Six Activity Seven Entire Project
PMAN Session Individual Assignment v Earned Value Management Earned Value Performance Measures aCalculate earned value performance parameters for each activity and for the cumulative project as of the end of week ; fill in the table below: ActivitySchedule Variance SVSchedule Performance Index SPICost Variance CVCost Performance Index CPI Activity One Activity Two Activity Three Activity Four Activity Five Activity Six Activity Seven Entire Project bIs the project ahead of schedule, on schedule, or behind schedule? What EVM information are you using to make this assessment and why? cIs the project over budget, under budget, or on budget? What EVM information are you using to make this assessment and why? Earned Value Forecasts aWhat is the value of the "Cumulative CPI" EstimateatCompletion EAC bUsing the "Mathematical" or "Overrun to Date" Estimateat Completion, what is the value of the EstimatetoComplete ETC cUsing the "Cumulative CPI times SPI" EstimateAtCompletion, how much more or less money other than the current budgeted amount will you need to finish the project? dHow much would the Cost Performance Index CPI have to change in order to complete the
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
