Question: pmaQ6 6. Your project is expected to run for three consecutive years. Your organization is introducing earned value management as part of the planning and
pmaQ6
6. Your project is expected to run for three consecutive years. Your organization is introducing earned value management as part of the planning and managing of this project. The project budget R100 000. The budget is for the three years. You are exactly 18 months into the project. 30 % of the total budget has been spent and 40% of the work is complete. The Project is behind schedule and running under budget. False or True