Question: PME 5 5 4 Question Set III 1 1 . The project team has finalized the set of guiding principles, and processes used to plan,
PME Question Set III
The project team has finalized the set of guiding principles, and processes used to plan, manage, execute and close a project. What is that?
a Project escalation system.
b Project governance approach.
c Delivery strategy of the project.
d Project management methodology.
The government of Ghana is implementing reforms in the electricity distribution sector using a private sector participation arrangement. What, in project management terms, is that an example of
a Delivery strategy.
b Governance system.
c Management methodology.
d Escalation matrix.
William's team has to tweak a preexisting project management methodology for the project at hand. Which of the following will they NOT adapt?
a Project cycle.
b Product development approach.
c Project delivery process.
d Governance arrangements.
In creating a project management methodology which item below will the team definitely have to develop as the most foundational?
a Product development approach.
b Responsibility assignment matrix.
c Project escalation system.
d Project governance arrangements.
Which of the following is the best general product delivery approach?
a Predictive cycle.
b Adaptive cycle.
c Project dependent.
d Hybrid cycle.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock