Question: PMT 4 7 2 3 . 2 ASSIGNMENT: WEEK 3 EXERCISES CH . 9 EXERCISE 8 Use the following information to compress one time unit

PMT4723.2 ASSIGNMENT: WEEK 3 EXERCISES
CH.9 EXERCISE 8
Use the following information to compress one time unit per move using the least-cost method.* Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total cost, and explain your choice if you have to choose between activities that cost the same. The indirect cost for each duration is $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, and $1,250 for 12 weeks.
Activity Crash Cost (slope) Maximum Crash Time Normal Time Normal Cost
A $003 $150
B $10014 $200
C $6013 $250
D $4014 $200
E $002 $250
F $3023 $200
G $2012 $250
H $6024 $300
I $20012 $200
Crash Round 1 B F G What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A D I Indirect cost (given): (Enter response)
Adjusted total project cost: (Enter response)
C E H
Crash Round 2 B F G What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A D I Indirect cost (given): (Enter response)
Adjusted total project cost: (Enter response)
C E H
What is the optimum cost-time schedule for the project? What is this cost?
(Enter response)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!