Question: PMT 4 7 2 3 . 2 ASSIGNMENT: WEEK 3 EXERCISES CH . 9 EXERCISE 8 Use the following information to compress one time unit
PMT ASSIGNMENT: WEEK EXERCISES
CH EXERCISE
Use the following information to compress one time unit per move using the leastcost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total cost, and explain your choice if you have to choose between activities that cost the same. The indirect cost for each duration is $ for weeks, $ for weeks, $ for weeks, $ for weeks, $ for weeks, and $ for weeks.
Activity Crash Cost slope Maximum Crash Time Normal Time Normal Cost
A $ $
B $ $
C $ $
D $ $
E $ $
F $ $
G $ $
H $ $
I $ $
Crash Round B F G What was crashed: Enter response
Adjusted total direct cost: Enter response
A D I Indirect cost given: Enter response
Adjusted total project cost: Enter response
C E H
Crash Round B F G What was crashed: Enter response
Adjusted total direct cost: Enter response
A D I Indirect cost given: Enter response
Adjusted total project cost: Enter response
C E H
What is the optimum costtime schedule for the project? What is this cost?
Enter response
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock