Question: PMW CH 1 3 Assigned Exercise 5 2 4 The data presented below and on the following pages have been collected for periods 1 through

PMW CH 13 Assigned Exercise 524
The data presented below and on the following pages have been collected for periods 1 through 5. The completed network diagram is give
below. Enter the values from the network into the baseline table given and calculate the cumulative baseline for the project. Complete th
status report tables given for periods 1-5. Compute the CPI, SPI, and PCIB values in the table given. Also compute EACI and TCPI where
requested. Make your project status report on the final page, providing the information and discussion requested.
Network Diagram:
Status Reports (to be completed)
Status Report: Ending Period
Status Report: Ending Period 2
Status Report: Ending Period 3
Status Report: Ending Period 4
Status Report: Ending Period 5
Show calculations in the table below for each quantity:
EACf (show calculations):
TCPI (show calculations):
How has the project progressed through Period 5?(Include in your report: CV, SV, SPI, CPI and PCIB and status of critical activities.)
 PMW CH 13 Assigned Exercise 524 The data presented below and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!