Question: point 1 2 3 4 6 7 5 309 25 Week Number Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Releases

point 1 2 3 4 6 7 5 309 25 Week Number Gross

point 1 2 3 4 6 7 5 309 25 Week Number Gross Requirements Scheduled Receipts Projected On Hand Net Requirements Planned Receipts Planned Releases 37 ? You produce tables for sale in big box stores. The above chart shows the current state. What quantity are the net requirements in week 5, assuming 2 week lead time? Type your