Question: Points ] CAMMIMS 1 6 9 . E . 0 1 6 . You may need to use the appropriate technology to answer this question.
Points
CAMMIMSE
You may need to use the appropriate technology to answer this question.
Management Decision Systems MDS is a consulting company that specializes in the development of decision support systems. MDS has a fourperson team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis.
tableTime WeeksActivityDescription,tableImmediatePredecessorOptimistic,Most Probable,PessimisticAReport generation,,BWeb scraping,,CTesting,A B
a Construct the project network. Submit a file with a maximum size of MB
no file selected
This answer has not been graded yet.
b Based solely on the critical path, estimate the probability that the project will be complete within weeks. Round your answer to four decimal places.
c Using all paths through the project network, estimate the probability that the project will be complete within weeks. Round your answer to four decimal places.
d Should you use the estimate in b or c
The probability estimate from b based on the critical path is more accurate.
The probability estimate from c based on both paths is more accurate.
The probability estimates from b and c are equal.
Need Help?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock