Question: points) Overall total cost or duration uncertainty for a project is clearly a high-level composite of many lower level sources of uncertainty. This is called:

points) "Overall total cost or duration
points) "Overall total cost or duration uncertainty for a project is clearly a high-level composite of many lower level sources of uncertainty." This is called: a) Definition of risk management b) Risk register c) Principle of hierarchy d) Principle of risk composition e) Principle of best-effort project management