Question: Points! U 03 In the following table the activibes with their precedence sequence and expected time (days) are listed for a project: A Activity Immediate

Points! U 03 In the following table the activibes
Points! U 03 In the following table the activibes with their precedence sequence and expected time (days) are listed for a project: A Activity Immediate Predecessors) D A B D Te -Immo A B B EF D GH Time (days) 0 2 4 5 5 5 2 3 5 a) The activities on the critical path are A-C-F.G. b) The project length is days