Question: PonIES) What is the Average Flow Time for the current order? Processing Time Days due from today Flow Time Task A 19 26 19 Task

PonIES) What is the Average Flow Time for the
PonIES) What is the Average Flow Time for the current order? Processing Time Days due from today Flow Time Task A 19 26 19 Task B 25 29 44 Task C 24 35 68 Task D 4 27 72 Task E 16 14 88 Question 28 (2 points) Saved