Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Crashing Cost
Immediate Predecessor(s)
A
4
3
$ 2 comma 200
$ 2 comma 800
long dash
B
2
1
$ 2 comma 300
$ 3 comma 100
long dash
C
3
3
$ 750
$ 750
long dash
D
8
4
$ 2 comma 400
$ 2 comma 680
A
E
6
3
$ 900
$ 1 comma 200
B
F
3
2
$ 3 comma 400
$ 4 comma 900
C
G
4
2
$ 1 comma 500
$ 1 comma 900
D, E
Part 2
a) What is the project completion date?
Based on the given information regarding the activities for the project, the project length=
16 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!