Porter Co. is analyzing two projects for the future. Assume that only one project can be selected.
| Project X | Project Y | |||||||
| Cost of machine | $ | 54,100 | $ | 62,800 | ||||
| Net cash flow: | ||||||||
| Year 1 | 19,100 | 4,200 | ||||||
| Year 2 | 19,100 | 27,400 | ||||||
| Year 3 | 19,100 | 27,400 | ||||||
| Year 4 | 0 | 21,000 | ||||||
The payback period in years for Project Y is:
a. 4.00
b. 3.18
c. 2.00
d. 3.82
e. 3.14