Question: Porter Co. is analyzing two projects for the future. Assume that only one project can be selected. Project X Project Y Cost of machine $
Porter Co. is analyzing two projects for the future. Assume that only one project can be selected.
| Project X | Project Y | |||||||
| Cost of machine | $ | 50,700 | $ | 69,600 | ||||
| Net cash flow: | ||||||||
| Year 1 | 18,000 | 4,800 | ||||||
| Year 2 | 18,000 | 31,400 | ||||||
| Year 3 | 18,000 | 31,400 | ||||||
| Year 4 | 0 | 24,000 | ||||||
The payback period in years for Project Y is: