Portstewart Boat builders Ltd has been asked to refit a boat for a customer; Skilled labour costing
Fantastic news! We've Found the answer you've been seeking!
Question:
Portstewart Boat builders Ltd has been asked to refit a boat for a customer; Skilled labour costing £8 per hour will be required for the refit. The workers will have to be taken off the production of canoes for resale for a total of 240 hours. The canoes are sold for£200 each and take 12 hours of skilled labour. The material cost of each canoe is £60.
What is the relevant cost of labour when assessing the viability of the refit contract?