Question: Potential problems can occur during activity duration estimating if omissions are made. All of these are remedies for omissions EXCEPT: a . rolling wave planning.
Potential problems can occur during activity duration estimating if omissions are made. All of these are remedies for omissions EXCEPT:
a rolling wave planning.
b checklists, templates, devil's advocate.
c refining scope and WBS
d lessons learned. successor activity. The wait for paint to dry is an example of a
a lead
b lag
c mandatory dependency
d discretionary dependency