Question: PPT Ch 13 Slide #1 AIA Doc G702-1992 Pay Request form shows the steps (20 point Question) You are the GC on a Project. It's

PPT Ch 13 Slide #1 AIA Doc G702-1992 Pay Request form shows the steps (20 point Question)

You are the GC on a Project. It's time to send your SECOND Pay Request.

On your G-702-1992 Pay Request you have an Original contract Sum contract amount of $2,725,897.00, Change Order #1 for $16,872.00, Change Order #2 for $36,002.00.. Retainage of 5.0% on Completed Work. The Total Contract Sum Includes Change Orders and Stored materials.

The Project is 30.6% complete That means 30.6% of the Total Completed and Strored to Date. Your Line #6 of Pay Request #1 (Line #7 entry on this Pay Request #2) is for __146,289.00___? Compute the amount of Pay Request #2. Your answer will be two(2) place accuracy $X,XXX,XXX.XX (Number of xx's here may not not actual answer number of digits)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!