Question: ppt d l o n , Question 1 7 4 pts In the Linear Scheduling Method, the time buffer is the vertical distance between represents
ppt
Question pts
In the Linear Scheduling Method, the time buffer is the vertical distance between represents free float of said activity at said location.
True
False