Question: PRACTICE CRASHING CRASHING EXERCISE #4 TASK PREDECESSOR DURATION SLACK CRASH TIME CRASHABLE DAYS NORMAL COST CRASH COST CRASH /UNIT A --- 3 2 100 300
PRACTICE CRASHING CRASHING EXERCISE #4
| TASK | PREDECESSOR | DURATION | SLACK | CRASH TIME | CRASHABLE DAYS | NORMAL COST | CRASH COST | CRASH /UNIT |
| A | --- | 3 |
| 2 |
| 100 | 300 |
|
| B | A | 5 |
| 3 |
| 700 | 1400 |
|
| C | A | 7 |
| 4 |
| 500 | 1500 |
|
| D | B, C | 3 |
| 2 |
| 400 | 900 |
|
| E | B | 5 |
| 4 |
| 300 | 900 |
|
| F | D | 4 |
| 3 |
| 100 | 300 |
|
| G | C | 2 |
| --- |
| 300 | ---- |
|
| H | E, F, G | 5 |
| 3 |
| 400 | 800 |
|
I know that the path is A-C-D-F-H IN 22 DAYS
CAN YOU ANSWER THE FOLLOWING IN DETAIL?
- How many crashable days are available for each task?
- What is the cheapest way to crash the project 6 days?
- Which tasks would be crashed?