Question: PRACTICE CRASHING CRASHING EXERCISE #4 TASK PREDECESSOR DURATION SLACK CRASH TIME CRASHABLE DAYS NORMAL COST CRASH COST CRASH /UNIT A --- 3 2 100 300

PRACTICE CRASHING CRASHING EXERCISE #4

TASK

PREDECESSOR

DURATION

SLACK

CRASH TIME

CRASHABLE DAYS

NORMAL COST

CRASH COST

CRASH /UNIT

A

---

3

2

100

300

B

A

5

3

700

1400

C

A

7

4

500

1500

D

B, C

3

2

400

900

E

B

5

4

300

900

F

D

4

3

100

300

G

C

2

---

300

----

H

E, F, G

5

3

400

800

I know that the path is A-C-D-F-H IN 22 DAYS

CAN YOU ANSWER THE FOLLOWING IN DETAIL?

  1. How many crashable days are available for each task?
  2. What is the cheapest way to crash the project 6 days?
    1. Which tasks would be crashed?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!