Question: Practice Question 1 A Project has the precedence relationships and optimistic, most likely, and pessimistic activity times provided in weeks quad Calculate the expected time

Practice Question 1
A Project has the precedence relationships and
optimistic, most likely, and pessimistic activity
times provided in weeks
quad Calculate the expected time (t_(e)) for each
activity
quad Calculate the variance, sigma^2, for each
activity
Work breakdown structure (WBS)
a. Identify activities / inputs
b. Organize activities into a work
breakdown structure
c. Determine precedents for activities
d. Estimate duration of each activity
Mean of activity time ( t_(e)
Variance of activity time ( sigma^)
Developing the project schedule
a. Create a precedence diagram
b. Calculations
Forward pass: Earliest start (ES) and earliest
finish (EF)
Backward pass: Latest start (LS) and latest
finish (LF)
quad Slack and Critical path
For each path calculate probability not late:
a. Sum of mean activity time TE(TE_(E))
b. Sum of variance of activity time ( sigma_(p))
c. z value
d. Probability of not being late
START
FINISH
Practice Question 1 A Project has the precedence

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!