Question: Practice Question 1 A Project has the precedence relationships and optimistic, most likely, and pessimistic activity times provided in weeks quad Calculate the expected time
Practice Question
A Project has the precedence relationships and
optimistic, most likely, and pessimistic activity
times provided in weeks
quad Calculate the expected time te for each
activity
quad Calculate the variance, sigma for each
activity
Work breakdown structure WBS
a Identify activities inputs
b Organize activities into a work
breakdown structure
c Determine precedents for activities
d Estimate duration of each activity
Mean of activity time te
Variance of activity time sigma
Developing the project schedule
a Create a precedence diagram
b Calculations
Forward pass: Earliest start ES and earliest
finish EF
Backward pass: Latest start LS and latest
finish LF
quad Slack and Critical path
For each path calculate probability not late:
a Sum of mean activity time TETEE
b Sum of variance of activity time sigmap
c z value
d Probability of not being late
START
FINISH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
