Question: Precedence Activity B Estimated Time (Weeks) 7 8 5 5 6 4 A B CD CE ED EF G H D E F 6 H

Precedence Activity B Estimated Time (Weeks) 7 8Precedence Activity B Estimated Time (Weeks) 7 8

Precedence Activity B Estimated Time (Weeks) 7 8 5 5 6 4 A B CD CE ED EF G H D E F 6 H 5 6 5. The slack associated with activity A is: a. O weeks b. 3 weeks C. 5 weeks d. 1 week. 6. The slack associated with activity Dis: a. 4 weeks b. 2 weeks C. 5 weeks d. Oweeks. 7. The slack associated with activity Cis: a. 4 weeks b. 2 weeks c. 1 week d. O weeks