Question: PREDE TIME ACTIVITY CESSO R (WEEKS) m b A 9 10 11 B - 4 10 16 C A 9 10 11 D B 5

PREDE TIME ACTIVITY CESSO R (WEEKS) m b A 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. Expected Time Variance A 10 10 10 8 HOAO b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network