Question: PREDE TIME ACTIVITY CESSO R (WEEKS) m b A 9 10 11 B - 4 10 16 C A 9 10 11 D B 5

 PREDE TIME ACTIVITY CESSO R (WEEKS) m b A 9 10

PREDE TIME ACTIVITY CESSO R (WEEKS) m b A 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. Expected Time Variance A 10 10 10 8 HOAO b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!