Question: Predecesso rs Crash Duration Crash Cost ( ) 9 0 5 Activity A B C Normal Duration 6 7 6 7 5 Saved Days 1
Predecesso rs Crash Duration Crash Cost Activity A B C Normal Duration Saved Days Normal Cost A A D E B F N DE G Using the data in the attachment, the duration of the critical path with no decimal places is days