Question: Predecessor Activities and Activity Times Activity Immediate Time (weeks) Predecessor(s) A 10 B 15 A.B 5 D A 20 E 8 F. D.E 7 EST

Predecessor Activities and Activity Times

Predecessor Activities and Activity Times Activity Immediate Time (weeks) Predecessor(s) A 10 B 15 A.B 5 D A 20 E 8 F. D.E 7 EST ECT LST LCT Start What is the slack of activity C? 0 1 week O O weeks 2 weeks O 3 or more weeks