Question: Prefferably hand written please. An IT project has been defined to contain the following list of activities along with their completion time and dependencies: Activity

Prefferably hand written please.
An IT project has been defined to contain the following list of activities along with their completion time and dependencies:
Activity No
Activity
Completion Time (weeks)
Dependency 1. Requirements gathering 4--2.
Requirements prioritization
313. Data analysis 414. Logical design 515. Physical design 63,46. Interface design 32,37. Report design 568. Coding 73,79. Testing and documenting 65,810. Installation and training 27,8,9
a. Draw a PERT chart for the project;
b. Calculate the earliest completion time for the project;
c. Show the critical path. [15 points]
Prefferably hand written please. An IT project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!