Question: Prepare a Gantt Chart based on Table 2. State the total duration of this project [8 M] Table 2. Research activity for health care information

Prepare a Gantt Chart based on Table 2. State the

Prepare a Gantt Chart based on Table 2. State the total duration of this project [8 M] Table 2. Research activity for health care information system project Activity Duration (weeks) Staff assigned Dependency 3 John Activity 1 1 Wong Activity 2 Activity 3 2 Wong John Activity 1. Activity 2 Activity 4 4 Tan Activity 3 Activity 5 Tan Activity 4 4 John Wong, Tan Activity 5 Activity 6