Question: Prepare a master production schedule based on the following information: Week: 1 2 3 4 5 6 7 8 Forecast 1 0 0 1 0

Prepare a master production schedule based on the following information:
Week: 12345678
Forecast 100100120120150150185180
Orders 10694654021920
Beginning inventory: 150
Schedule production whenever projected-on-hand drops below 20.
The production lot size is 250 units.
What is the difference between the Available to Promise Inventory and the Projected On Hand Inventory) for Period 7?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!