Question: Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule

Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are follows: Click here for the Excel Data File Use a production lot size of 75 units and no beginning inventory. (Leave no cells blank - be certain to enter "0" wherever required.)