Question: Prepare a master schedule given this information: The forecast for each week of an eight - week schedule is 6 0 units. The MPS rule

Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:
Week Customer Orders
152
238
323
412
Use a production lot size of 100 units and no beginning inventory.\table[[,June,July],[,1,2,3,4,5,6,7,8],[Forecast,60,60,60,60,60,60,60,60],[Customer Orders,52,38,23,12,0,0,0,],[Projected On-Hand Inventory,,,,,,,,],[MPS,,,,,,,,],[ATP,,,,,,,,]]
 Prepare a master schedule given this information: The forecast for each

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!