Question: Prepare a master schedule given this information: The forecast for each week of an eight - week schedule is 6 0 units. The MPS rule
Prepare a master schedule given this information: The forecast for each week of an eightweek schedule is units. The MPS rule is to schedule production if the projected onhand inventory would be negative without it Customer orders committed are as follows:
tableWeekCustomer Orders
Use a production lot size of units and no beginning inventory. In the ATP row, enter a value of zero in any periods where ATP should not be calculated. Leave no cells blank be certain to enter O wherever required.
tableJune,JulyForecastCustomer Orders,Projected OnHand Inventory,I,,,,,,MPSkATP$