Question: Prepare a Master Schedule like that shown in Figure 11.11 given the following information: The forecast for each week of an eight-week schedule is 50
Prepare a Master Schedule like that shown in Figure 11.11 given the following information: The forecast for each week of an eight-week schedule is 50 units. The MPS tule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 52 2 35 3 20 4 12 Use a production lot size of 75 units and no beginning inventory.
Step by Step Solution
There are 3 Steps involved in it