Question: Prepare an MRP plan for scissors using the diagram and information below. Lead times are one week for each component and final scissor assembly, but




Prepare an MRP plan for scissors using the diagram and information below. Lead times are one week for each component and final scissor assembly, but two weeks for the plastic grips. Six hundred pairs of scissors are needed in Week 6 . The company uses lot-for-lot ordering for all items except screws which must be ordered in packages of 180. Note: There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand. (Leave no cells blank - be certain to enter 0 wherever required.)