Question: Preventive action _ _ _ _ _ _ _ _ _ _ _ _ . a . realigns the performance of the project work with
Preventive action
a realigns the performance of the project work with the project management plan
b seeks to ensure the future performance of the project work is aligned with the project management plan
c is primarily addressed in the Control Quality process
d modifies a nonconforming product or product subcomponent