Question: Previous Page Next Page Page 5 Question 5 (5 points) Listen A company used 5.200 Direct Labor Hours to produce 3,000 units this year. The
Previous Page Next Page Page 5 Question 5 (5 points) Listen A company used 5.200 Direct Labor Hours to produce 3,000 units this year. The company had expected to produce only 2,500 using 1.5 labor hours per unit. If the actual wage rate was $16.50, but the budgeted wage rate had been $15, what was the labor efficiency variance? $10.500 Unfavorable $11,550 Unfavorable $7,500 Unfavorable 58.250 Unfavorable Previous Page Next Page Page 5 of 20 Ede Your FH Par Modeling resume CAC Type here to search oll