Question: PRI 5 0 0 3 SBM 1 2 0 1 - W 7 - Tutorial Question - 2 - Do a CPM analysis for the
PRI SBM W Tutorial Question
Do a CPM analysis for the following in which the key resource is a tractor. There are three tractors available to the project. Activities A and D require one tractor to complete while Activities B C E and F require two tractors.
Develop a resourceconstrained schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do Record the early start ES late finish LF and slack SL for the new sehedule.