Question: primary purpose of DRUM, BUFFER, ROPE ( DBR ) scheduling in the Theory of Constraints ( TOC ) is to synchronize and optimize production processes
primary purpose of DRUM, BUFFER, ROPE DBR scheduling in the Theory of Constraints TOC is to synchronize and optimize production processes to maximize throughput. It helps identify and manage the constraint DRUM protect the system from disruptions BUFFER and ensure that work is released into the system at the right time ROPE