Question: Problem 0 9 . 0 2 0 - Benefit / Cost analysis of a single project A consultant, after 3 months of work, reported that
Problem BenefitCost analysis of a single project
A consultant, after months of work, reported that the modified BC ratio for a cityowned hospital heliport project is If the initial
cost is $ million and the annual benefits are $ what is the amount of the annual M&O costs used in the calculation? The
report stated that a discount rate of per year and an estimated life of years were used. Round the final answer to three
decimal places.
The & cost is $