Question: Problem 1 0 - 2 ( LO 1 0 - 3 ) The number of daily calls... The number of daily calls for the repair

Problem 10-2(LO 10-3) The number of daily calls...
The number of daily calls for the repair of Speedy copy machines has been recorded as follows.
October Calls
192
2127
3106
4165
5125
6111
7178
897
(Round all answers to 1 decimal place.)
a. Prepare three-period moving-average forecasts for the data. What is the error on each day?
b. Prepare three-period weighted-moving-average forecasts using weights of W1=0.5, W2=0.3, W3=0.2. What is the error on each day?
c. Calculate the arithmetic sum of errors and the absolute deviation for both methods.
Which of the two forecasts is better?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!