Question: Problem 1 1 - 2 1 ( Algo ) Prepare a master schedule given this information: The forecast for each week of an eight -

Problem 11-21(Algo)
Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:
\table[[Week,Customer Orders],[1,54],[2,38],[3,25],[4,20]]
Use a production lot size of 73 units and no beginning inventory. (In the ATP row, enter a value of 0(zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "O" wherever required.)
\table[[,June,July],[,1,2,3,4,5,6,7,8],[Forecast,60,60,60,60,60,60,60,60],[Customer Orders,54,38,25,20,0,0,0,0],[Projected On-Han,,,,,,,,],[MPS,,,,,,,,],[ATP,,,,,,,,]]
 Problem 11-21(Algo) Prepare a master schedule given this information: The forecast

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!