Question: Problem 1 (10 points) Level the resources for the following schedule. Draw two manpower curves for the project: one before leveling and one after leveling.

Problem 1 (10 points) Level the resources for the
Problem 1 (10 points) Level the resources for the following schedule. Draw two manpower curves for the project: one before leveling and one after leveling. Indicate the peak number of workers in both cases. Use the early start dates for the "before leveling" schedule. Predecessor Activity A B C D E F Milestone Duration 5 3 5 2 2 3 A A A C E B, C, D, E, F Milestone Milestone Milestone Milestone Milestone A A G,H,I,J,K,L,M Workers 5 8 10 6 12 6 0 9 10 8 12 12 8 6 4 H I L Z 3