Question: Problem 1 . ( 2 0 pints ) Consider the following activities, their predecessors and the three time estimates ( days ) : table
Problem pints
Consider the following activities, their predecessors and the three time estimates days:
tableActivityPredecessor,Optimistic aMost Probable mPessimistic btableExpectedValueVarianceABACBDBEDFDGDHCEFGIHJHGI,JLKLM
a Compute the expected completion time the variance for each activity.
b Draw a network and determine the critical path based on the expected completion times.
c What is the probability of finishing the project in less than days?
d What is the probability of finishing the project in less than days?