Question: Problem 1 . ( 2 0 pints ) Consider the following activities, their predecessors and the three time estimates ( days ) : table

Problem 1.(20 pints)
Consider the following activities, their predecessors and the three time estimates (days):
\table[[Activity,Predecessor,Optimistic (a),Most Probable (m),Pessimistic (b),\table[[Expected],[Value]],Variance],[A,,2,4,6,,],[B,A,3,5,7,,],[C,B,1,3,5,,],[D,B,8,10,12,,],[E,D,6,8,10,,],[F,D,3,4,5,,],[G,D,4,6,8,,],[H,C,E,F,G,7,8,9,,],[I,H,3,5,7,,],[J,H,3,6,9,,],[G,I,3,6,9,,],[7,J,1,2,3,,],[L,K,L,6,12,18,,],[M,,,,,,],[,,,,,,]]
(a) Compute the expected completion time the variance for each activity.
(b) Draw a network and determine the critical path based on the expected completion times.
(c) What is the probability of finishing the project in less than 48 days?
(d) What is the probability of finishing the project in less than 51 days?
 Problem 1.(20 pints) Consider the following activities, their predecessors and the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!