Question: Problem 1 2 - 1 5 ( Algo ) Internal BusIness Process Performance Measures [ LO 1 2 - 3 ] Tombro Industries is automating
Problem Algo Internal BusIness Process Performance Measures LO
Tombro Industries is automating one of its plants and developing a flexible manufacturing system. In an effort to revise its performance
measurement system, the company gathered the following data for the last four months:
The president read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but
no one is sure how to compute them. You have been asked to assist the company and gathered the following data:
Requlred:
a Compute the throughput time for each month.
b Compute the manufacturing cycle efficiency MCE for each month.
Compute the delivery cycle time for each month.
a Refer to the inspection time, process time, and so forth, given for month Assume in month the inspection time, process time,
and so forth are the same as for month except the company is able to completely eliminate the queue time using Lean Production.
Compute the new throughput time and MCE.
b Refer to the inspection time, process time, and so forth, given for month Assume in month the inspection time, process time,
and so forth are the same as in month except the company is able to eliminate the queue time and inspection time using Lean
Production. Compute the new throughput time and MCE.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock