Question: Problem 1 2 - 2 8 Project Evaluation [ LO 3 ] Suppose you have been hired as a financial consultant to Defense Electronics, Incorporated

Problem 12-28 Project Evaluation [LO 3]
Suppose you have been hired as a financial consultant to Defense Electronics, Incorporated (DEI), a large, publicly traded firm that is
the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas to
produce a new line of RDSs. This will be a five-year project. The company bought some land three years ago for $7.2 million in
anticipation of using it as a toxic dump site for waste chemicals, but it built a piping system to safely discard the chemicals instead. If
the land were sold today, the net proceeds would be $7.66 million after taxes. In five years, the land will be worth $7.96 million after
taxes. The company wants to build its new manufacturing plant on this land; the plant will cost $13.24 million to build. The following
market data on DEl's securities are current:
DEl's tax rate is 21 percent. The project requires $855,000 in initial net working capital investment to get operational.
a. Calculate the project's Time 0 cash flow, taking into account all side effects. Assume that any NWC raised does not require
floatation costs.
Note: A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answer in
dollars, not millions of dollars, e.g.,1,234,567. b. The new RDS project is somewhat riskier than a typical project for DEI, primarily because the plant is being located overseas.
Management has told you to use an adjustment factor of +3 percent to account for this increased riskiness. Calculate the
appropriate discount rate to use when evaluating DEl's project.
Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g.,32.16.
c. The manufacturing plant has an eight-year tax life, and DEI uses straight-line depreciation. At the end of the project (i.e., the end of
Year 5), the plant can be scrapped for $1.56 million. What is the aftertax salvage value of this manufacturing plant?
Note: Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, e.g.,1,234,567.
d. The company will incur $2,360,000 in annual fixed costs. The plan is to manufacture 13,600 RDSs per year and sell them at $11,000
per machine; the variable production costs are $10,200 per RDS. What is the annual operating cash flow, OCF, from this project?
Note: Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, e.g.,1,234,567.
e. Calculate the project's net present value.
Note: Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, rounded to 2 decimal
places, e.g.,1,234,567.89
f. Calculate the project's internal rate of return.
Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g.,32.16.
 Problem 12-28 Project Evaluation [LO 3] Suppose you have been hired

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!